Tower Avenue Construction Update - September 16, 2013

For More Information:
Chris Ouellette, Regional Communications Manager
(715) 833-9814/828-9471


Tower Avenue Construction Update – September 16, 2013


Work completed since last update:

•Concrete Sidewalk was placed in various locations between Winter Street and 12thStreet.
•Concrete left turn lanes, parking lanes and intersections were completed between 12thand Belknap.
•Concrete curb and gutter has been completed on all side streets and Tower Avenue between 12th and Belknap Street.
•The Railroad finished replacing the southern crossing.
•All screen walls and planters have been poured and brick masonry has been installed in the intersection planters from 4th to 12th Street.
•Topsoil has been completed between 4th and 8th Streets.
•Light bases have been installed between 12th and 14th Street.

Anticipated work schedule for the week of Sept. 16, 2013:

•Concrete sidewalk is scheduled to continue between Winter Street and 12th Street.
•Brick Masonry is scheduled to be installed in the intersection planters between 13th and 14th Street.
•Asphalt paving (lower layer) is scheduled for Broadway – 14th Street.
•Topsoil and planting soil is scheduled to continue in the turf and planting areas.
•Cleaning and sealing of concrete pavement joints is scheduled between 4th and 8th street.
•Light bases are going to continue to be installed between 14th and Belknap Street and the electrical contractor anticipates beginning to assemble light poles.

Next Weekly Public Meeting:  Wednesday, Sept. 18 at 2 p.m. at the Old Post Office Building, 1401 Tower Ave.