Tower Avenue-Superior Road Construction Update


Work completed since last update:

•Concrete sidewalk has been placed in various locations between 12thStreet and Belknap Street

•Topsoil restoration complete to 11th Street

•Concrete safety islands installed at Hammond Avenue and 3rd Street. Red concrete placed at 12th and 13th Street intersections

•Asphalt patching completed in various parking areas between 4th Street and Broadway Street

•Beginning of light pole installation between Winter Street and 12thStreet


Anticipated work schedule for the week of September 30, 2013:

•Concrete sidewalk work is scheduled to be completed between 13th and Belknap Street

•Tree grate boarders and light poles to be placed between Winter and Belknap Streets

•New curb, gutter, sidewalk, and asphalt is scheduled to be installed at 3rd Street

•Asphalt paving is scheduled to continue on all side streets as well as asphalt patching in parking lots. General restoration and cleaning will continue project wide.

•Scheduled to finish placing planting soil

•Begin pavement markings and permanent signs


Next Weekly Public Meeting:  Wednesday, Oct. 2 at 2 p.m. at the Old Post Office Building