    Next Contractors Meeting: Monday, August 7th, 1:00 p.m. at the SBID Office. 823 Belknap Street, Ste. L-10 (Lower Level)

    Please note:
    There is no turning onto Belknap from Tower Avenue.  The Superior Police Department has been monitoring the intersection, please obey all construction signs to avoid back-ups. Thank you!

    Project Staging, Schedule and Traffic Overview:

    Banks Avenue to John Avenue (West End)                      Traffic Control
    South Side Construction       4/11/17 – 7/10/17     Bidirectional on the north side.
    North Side Construction        7/11/17 – 9/1/17     Bidirectional on the south side.
    Median Construction              9/5/17 – 10/6//17     Traffic in the outside lanes.
    Birch Avenue to Hill Avenue (East End)                            Traffic Control
    South Side Construction       4/17/17 – 7/30/17     Bidirectional on the north side.
    North Side Construction        8/1/17 – 10/16/17     Bidirectional on the south side.
    Median Construction              10/17/17 – 11/17/17   Traffic in the outside lanes                                                                           
    Project Detours – There is a signed truck detour utilizing the City of Superior Truck Route. There is also an alternative detour route signed for other traffic to bypass the project.  

    Traffic impacts
    - Motorists can expect to encounter single lane closures and lane shifts as the project progresses
    - Hill Avenue is now closed.  Please use Elm Avenue as an alternative route.
    - North Banks Avenue will be closed starting Monday, July 31. 
    - There is a signed truck detour utilizing the City of Superior Truck Route.
    - There is an alternative detour route signed for other traffic to bypass the project. 

    Work Completed since last update:
    West End - Banks Avenue to John Avenue
    - Traffic has switched to south lanes
    East End - Birch Avenue to Hill Avenue

    - Mainline concrete pavement Hill to Railroad tracks

    Anticipated work schedule for next week: 
    West End - Banks Avenue to John Avenue
    - North Side removals
    - Concrete bases for street lights and signal bases
    - Grading
    East End - Birch Avenue to Hill Avenue
    - Concrete Paving - Railroad tracks to Catlin Avenue
    - Concrete Curb & Gutter
    - Concrete Sidewalk